In the above two-area system, a total of five generators and five step-down transformers were implemented into the system. These two areas are interconnected by a tie-line between busbar 8 and busbar 10. Using the Load Flow Analysis where Area 1 exports 400MW to Area 2, the parameters of the five generators and other relevant parameters were calculated as shown.
G1, G2 and G3 are conventional steam generators generating three conventional steam units.- G4 is a gas generator generating one gas turbine.
G5 is a steam generator generating one steam turbine.